How To Setup a Factory ?

       The Requested Documents :
            1 - An application named b Ismailia governor with data of the applicant and the
             kind of the activity and the requested area.
            2 - Economic studies about the presented project.
            3 - Bank financial situation from one of the banks with the name the of applicant.
            4 - Digraph of the project.
            5 - Catalogue of used equipment and machines for the project.
            6 - How to get rid of the trash.
            7 - Environmental study about the project.
            8 - Acceptances of general manufacturing authority just in case it is needed.

       Payment’s system:
            1 - The accepted applicant is informed to receive deposit’s order of the bank
             from the services committee of the first and second industrial zones.
             the price of meter is 1,60 pounds (the price of land and services).
            2 - The investor presents the deposit order after paying then the accepted.
            3 - The annual maintenance expenses are paid in return of the services committee
             does all kinds of the services committee does all kinds of maintenance and
             cleaning, tree planting, lighting, painting, pesticides.

       The executive time:
                        All the above mentioned documents submitted to the board then
             the technical committee studies it and decides what it sees.This is in a month
             after presenting those documents. The technical committee’s opinion is offered to
             the board. Then the governor signs the application.